Existence Risks
Words on this page that have been underlined and italicized can be found in the glossary on the bottom of the page.
Overview
An existence risk is an activity which may or may not occur. By default:
- All activities start out with an existence probability of 100%, meaning they will occur in every iteration during the simulation
- When an existence probability of less than 100% is entered, the duration is zeroed out for those iterations that it's sampled as not occurring
Example | Option 1 | Option 2 |
---|---|---|
Schedule resubmittal | Including in the duration range results in an overly pessimistic distribution on the submittal activity | Successor activity to schedule submittal with 0 day duration, existence probability <100% |
Risk of encountering contaminated soil during excavation | Including as a risk impact may conflate weather modeling | Insert activity with 0 day duration, existence probability <100% |
Designating Existence Risks
- Click the Ranging icon.
- Click the View button above the top list and choose Duration and Cost.
- Scroll to the desired activity.
- Enter a value less than 100% in the Existence Probability column.
Tip
To turn on the Existence Probability column, see Customizing Columns.