Risk-Activity Impacts
Words on this page that have been underlined and italicized can be found in the glossary on the bottom of the page.
Tip
When a risk's schedule impact occurs, an activity's duration is extended by the specified impact in working days. If you want to model a delay to the activity, see Delay Risks below.
Inherited Assignments
In NetRisk, quantitative probability and impact may be entered at the risk/scenario-level in the risk register.
- This saves time, as the probability and impact are inherited automatically and do not need to be entered one-by-one
- Subsequent modifications to the probability or impact are automatically carried down to each assignment
An inherited assignment is identified by an icon next to each value that has been inherited.
- Click the Risk icon.
- Click the View button above the top list and choose Risk Register.
- Select the desired risk or scenario in the upper list.
- Enter a value in the Probability (Quantitative) column.
- In the Distribution Type column for schedule and/or cost, click to choose a desired distribution type.
Enter a value in each of the required columns.
Required columns will display a Warning icon. If none of the required columns are visible, they must be turned on (see Customizing Columns). So long as any column contains a warning, the entire row will be colored orange (for a risk/scenario with no inherited assignments) or red (for a risk/scenario with inherited assignments).
In the lower list, next to the desired activity(s), check the box in the Schedule column to assign a schedule impact and next to the Cost column to assign a cost impact.
Tip
To force all activity assignments to the top, click the Sort icon, uncheck Organize by WBS, click Assign twice until the down arrow shows up next to it (descending order), and then make sure the list is then scrolled all the way to the top.
Un-inheriting Risks/Scenarios
If an inherited risk assignment has any value modified at the activity level, any modifications to the probability or impact in the register will no longer be carried down to each assignment.
Individual vs. Grouped Assignments
By default, all assignments underneath a given risk with the same probability of occurrence will be impacted in the same iterations as each other as a group. To impact activities individually, uncheck the box in the Correlate Probability column in the lower list. If the column isn't visible, it must be turned on first (see Customizing Columns). For more on individual vs. group assignments, see the Risks section in The Risk Register.
Removing an Assignment
An assignment can be removed from the selected scenario or from all scenarios underneath the same risk - the choice is made when unchecking the box.
- Click the Risk icon.
- Click the View button above the top list and choose Risk Register.
- Select the desired risk or scenario in the upper list.
- In the lower list, next to the desired activity(s), uncheck the box in the Schedule column to remove schedule impact or in the Cost column to remove cost impact.
Activity View
Whereas the Risk Register view is useful for assigning activities to designated risks, the All Activities view is useful for assigning risks to designated activities.
- Click the Risk icon.
- Click the View button above the top list and choose All Activities.
- Select the desired activity in the upper list.
- In the lower list, check the box next to the desired risk in the Schedule column or Cost column accordingly.
In the activity view, risks cannot be created or modified.
Sampling In Parallel vs. In Series
By default, all risk schedule impacts are sampled in parallel. This can be set individually for each risk impact by clicking the dropdown in the Sampling Order column and choosing between In Series and In Parallel.
Option | Definition |
---|---|
In Parallel | Largest impact taken |
In Series | All impacts added together |
Probabilistic Branching
A few basic basic probabilistic branching scenarios can be modeled in NetRisk. All methods require setting up the different branches in the schedule file with their deterministic durations. Once in NetRisk, each activity is given a duration distribution of 0 days (constant). Next, a risk is created for each activity where the schedule impact entered on the risk becomes the activity's duration distribution. And finally, the risks are correlated per the table below.
Scenario | Description | Process |
---|---|---|
A | A chain of activities all occur, or neither occurs | Create 1 risk per activity in the chain. Enter the same probability for each risk (e.g. 25%), assign them to each activity in the chain, and then correlate the existence of each risk to the first risk with a coefficient of 1. |
B | Either one activity occurs or another activity occurs | Create 2 risks with unique probabilities that add up to 100% (e.g. 25% and 75%), assign them to each activity, and then correlate the existence of the second risk to the first risk with a coefficient of -1. |
C | Either one chain of activities occur or another chain of activities occur | Create 1 risk for each activity in the first chain. Enter the same probability for each risk (e.g. 25%), assign them to each activity in the chain, and then correlate the existence of each risk to the first risk with a coefficient of 1. Create 1 risk for each activity in the second chain. Enter the same probability for each risk AND which also adds up to 100% when combined with the probability of the risks for chain 1 (e.g. 75%). Assign them to each activity in the chain, and then correlate the existence of each risk in this chain to the first risk in this chain with a coefficient of 1. Finally, correlate the existence of any risk in the first chain to any risk in the second chain with a coefficient of -1. |
For more info on correlations, see Risk-to-Risk Existence Correlations.
Delay Risks
To model a risk which delays an activity, one of the following methods can be used:
Option | Considerations | Process |
---|---|---|
Risk-based approach | Doesn't impact deterministic finish date | Add a 0-day activity to the schedule file as a predecessor to the activity to be delayed. Assign the risk to the 0-day activity. When the risk occurs, the 0-day activity's duration will extend, thus delaying the successor. |
Activity-based approach | Does impact deterministic finish date | Add an activity to the schedule file as a predecessor to the activity. In NetRisk, enter a duration range to represent the risk impact. Set the Existence Probability to represent the likelihood of the risk occuring. For more info, see Existence Risks. |
Choosing Distribution Types
Choosing a distribution type should be determined by the level of confidence in the values being chosen. When entering the range, the minimum is interpreted as the optimistic estimate, or best case scenario; the most likely is interpreted to be the most likely estimate; and the maximum is interpreted as the pessimistic, or worst case scenario.
Distribution Type | When to Use... |
---|---|
Constant |
|
Beta-Pert |
|
Log-Normal |
|
Normal |
|
Triangular |
|
Trigen |
|
Uniform |
|
Copy/Paste/Fill Down
Once entered, probability and impact ranges can be copied and pasted or filled down to save time. For details, see Interface Tour.
Available Table Columns
For details on customizing columns, filtering, sorting, and organizing by WBS, see Interface Tour.
For qualitative columns, see The Risk Register.